LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

Vineyard Wind sees more permitting delays, but stays on track to be first in U.S. race to build offshore farms 

Credit:  Noah Asimow | The Vineyard Gazette | Monday, November 23, 2020 | vineyardgazette.com ~~

Vineyard Wind, the international business consortium that plans to build the nation’s largest offshore wind farm 15 miles south of Martha’s Vineyard, has been hit with yet another delay after a federal agency moved back its review timeline for a key permitting document last week.

The $2.8 billion dollar offshore energy project was originally expected to have its Final Environmental Impact Statement (FEIS) completed earlier this week, with a final recorded decision before the New Year. The impact statement is required before the federal government can make a decision on the project.

But the Bureau of Ocean Energy Management – the federal agency responsible for issuing the environmental impact statement and permitting the project – updated its timeline late last week, moving back the expected date for the final impact statement to Dec. 11. The BOEM online timetable for Vineyard Wind now lists Jan. 15, 2021 as its expected date to issue a formal record of decision on the development.

A BOEM spokesman said in an email that the agency is still reviewing a mountain of correspondence related to the project.

More than 13,000 comments were received during a public comment period on the supplemental environmental impact statement, the spokesman said. “BOEM continues to work with cooperating agencies in the review of these comments.”

The expected decision date is less than a week before the Trump administration is slated to leave office. The timetable now states that the final completion of all permitting and environmental review on the project is expected by March 18, 2021.

Despite the setbacks, as the race to build offshore wind farms heats up, Vineyard Wind remains on track to be the first industrial-scale wind farm in the United States.

Headquartered in New Bedford, the company is a joint, 50-50 venture between Copenhagen Infrastructure Projects and Avangrid Renewables.

In an emailed statement, a spokesman for Vineyard Wind said the delay would not affect the timeline for the project, which is expected to be online by 2023.

“Minor delays like this are not uncommon and we look forward to publication of the FEIS on Dec. 11,” spokesman Andrew Doba said. “We are confident that we’ll be able to make the investment decision by mid-2021 as planned and deliver the project in the announced time frame.”

Vineyard Wind 1, as the project is formally known, includes the construction of approximately 80 turbines and two undersea cables that will connect the wind farm to mainland Cape Cod at a switching station in Barnstable. The undersea cables will run about a mile east of Chappaquiddick.

The project is expected to generate 800 megawatts of wind energy and power up to 400,000 homes in southeastern Massachusetts.

Mayflower Wind, which plans to build a wind farm in a federal lease block southeast of Vineyard Wind, has also recently begun its permitting process.

Vineyard Wind has now received all its requisite state and local permitting, after a process that was bumpy at times. The Edgartown conservation commission denied the undersea cable part of the project but later reached agreement with the wind farm developers for the cable.

Concerns from fishermen and marine navigation have slowed the permitting process at both the state and local level.

Federal permitting has been even more of a challenge for Vineyard Wind, which has been hit with numerous delays to the final environmental impact statement over the past 18 months after federal regulators said they would evaluate the project in the context of cumulative impacts of all planned offshore wind development along the Atlantic coast.

The change forced BOEM to issue a new supplemental impact statement that considered the project’s impacts within the broader ecosystem of all future coastal wind development. A draft of the statement was released this past summer.

The most recent delay comes just as Vineyard Wind signed an agreement with ISO New England to deliver energy to the grid once the project comes online. The company had already been cleared to enter into power purchase agreements with state electric distribution companies.

Source:  Noah Asimow | The Vineyard Gazette | Monday, November 23, 2020 | vineyardgazette.com

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI M TG TS G Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky