Thunderhead Conditional Use Permit approved
Credit: By Lynell Morgan | The Elgin Review | December 5, 2018 | www.elginreview.com ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
For close to two hours, the fate of the proposed Thunderhead Wind Energy farm hung in the balance.
Then, just before noon Tuesday, the Antelope County Commissioners approved a conditional use permit by a 4-0-1 vote (chairman LeRoy Kerkman abstaining).
Process for Thunderhead
The vote means it’s very likely, sometime in 2019, work will begin on the wind farm with towers to be located primarily in Antelope County, some in Wheeler County. As many as 170 wind towers could be built as part of Thunderhead.
Landowners and others interested in the wind farm overflowed the commissioners’ meeting room for the hearing.
In approving the permit application, the commissioners accepted the Antelope County Planning Commission’s recommendation to approve the permit with the conditions’ they noted.
There was one additional condition added. County Road Boss Casey Dittrich asked the commissioners to include an assessment of $2,500 per day, per mile for roads which the county must close due to damage caused during wind farm construction. Dittrich said there were “serious growing pains” with subcontractors for Upstream Wind Energy farm located north of Neligh. Issues arose with farmers, during harvest, unable to get to their fields because of roads being closed due to the wind farm. “I think Invenergy is ready to ‘play ball’ with that,” Dittrich said.
As part of the public hearing, individuals both for and against the wind farm gave testimony, much of it verbal, but some written.
Additional conditions
Conditions – Other conditions of note with the approved permit are:
• Turbines shall not move more than 900 feet in any direction from the specific proposed location in Exhibit A and shall be sited on parcels identified in the Participating Landowner List (See Condition #3.) All County zoning setbacks and conditions of this permit will apply and must be met in order to place turbines on the Property.
• All turbines will be installed with a Winter Ice Operation Mode (WIOM) control algorithm.
See the complete story in this week’s issue of The Elgin Review
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
(via Stripe) |
(via Paypal) |
Share: