LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.
»» Search…

News Watch Home

FERC orders Indiana wind project to the back of the queue 

Credit:  By Michael Kuser | RTO Insider | February 12, 2018 | www.rtoinsider.com ~~

Share:

e-mail X FB LI M TG TS G Share


FERC ruled Friday that the developer of a proposed 1,500-MW Indiana wind farm must go to the end of the interconnection queue to move its point of interconnection (POI) 2.9 miles.

The commission’s Feb. 9 order rejected Harvest Wind’s request for a waiver allowing it to change the POI without triggering the “material modification” language under PJM’s Tariff. FERC sided with PJM in requiring a new queue application and facilities study (ER18-615).

Colorado-based Renewable Energy Systems Americas acquired the Harvest Wind project after the previous developer agreed in late 2016 to move to a second POI after AEP Indiana Michigan Transmission said the original was not a suitable spot for the wind farm’s 765-kV switchyard.

RES Americas said it learned in fall 2017 that the new location, POI 2, had some of the same problems as the original location, including wetlands and endangered species concerns. In addition, noise from the switchyard’s transformers would be too loud because of nearby houses, the company said in its Jan. 5 waiver request.

The developer said its proposed interconnection, POI 3, is “electrically identical” to the current location because it is just 2.9 miles away on the same 765-kV transmission line.

PJM opposed the request, arguing that the waiver would delay other projects in the queue because of the size of the wind project and the need for transmission restudies.

The commission agreed with PJM, finding that “Harvest Wind has not sufficiently demonstrated that it acted in good faith. Harvest Wind states that it became aware in September 2016 that both POI 1 and POI 2 presented some complicating factors due to site topology, but at that time it did not believe these factors were insurmountable. … Moreover, Harvest Wind fails to explain why it did not discover these additional complications for almost a year after initially being put on notice that complications existed at POI 1 and POI 2, demonstrating a lack of due diligence on Harvest Wind’s part.

“Harvest Wind has not sufficiently demonstrated that granting the waiver request will not have undesirable consequences or harm third parties,” the commission continued. “We agree with PJM that changing the point of interconnection at this late stage would introduce uncertainty that could well impact other lower-queued interconnection customers and that such restudy of the point of interconnection would require reassessment of protection, requiring the expenditure of time and resources, thus burdening and harming other parties.”

RES Americas said in its waiver request that it might be forced to abandon the project if the waiver were not approved.

An RES Americas spokesman said the company was “planning to proceed with the project” but did not say why a delay might force it to abandon it.

Source:  By Michael Kuser | RTO Insider | February 12, 2018 | www.rtoinsider.com

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)


News Watch Home

CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.