Judges certify transmission line ‘re-think’
Credit: Fredericksburg Standard, www.fredericksburgstandard.com 8 September 2010 ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
A reevaluation of the need for wind energy transmission lines from Schleicher County (McCamey D) to the Kendall substation to Gillespie (M-K-G) seems certain following a ruling Sept. 1 by two Administrative Law Judges from the State Office of Administrative Hearings (SOAH).
Judges Wendy Harvel and Travis Vickery have certified two issues for Public Utilities Commission consideration at their next meeting Wednesday, Sept. 15.
First to be considered is whether the Lower Colorado River Authority Transmission Services Corporation’s (LCRA TSC) application for the 345-kV Competitive Renewable Energy Zone (CREZ) lines in Schleicher, Sutton, Menard, Kimble, Mason, Gillespie, Kerr and Kendall counties should be dismissed without prejudice pending the results of a further study by the Energy Reliability Council of Texas (ERCOT) on the need for the line.
Second, should the need for the M-K-G line be added to the PUC’s discussion of the Gillespie-to-Newton line (G-N)?
All parties have agreed to submit information to PUC by today.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
(via Stripe) |
(via Paypal) |
Share: