Windfarm progress in Adair and Schuyler counties affecting roads and bridges
Credit: KTTN-FM 92.3 and KGOZ-FM 101.7 | August 21, 2020 | www.kttn.com ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
Adair and Schuyler Counties have seen changes over the last few months with windfarm turbines going up in the area. Construction of the turbines is ongoing and is expected to be completed by the end of the year.
Heavy loads of equipment and concrete have caused deterioration of routes in the area. Speed limits have been reduced on several routes and bridge weight postings have been issued to help with the declining conditions of the roads.
“We ask that drivers follow these new speed limits, bridge postings and other traffic control that is in place,” said District Engineer Paula Gough.
Crews continue to make short-term repairs to keep the roads open, while the windfarm company is also repairing locations.
“At the conclusion of the windfarm work, MoDOT will be completing more substantial long-term repairs to restore the routes to their original condition prior to wind farm construction,” Gough said.
Funding for all repairs is being provided by an agreement between MoDOT and the windfarm company.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
(via Stripe) |
(via Paypal) |
Share: