LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

Illinois Supreme Court rules on Rock Island Clean Line project 

Credit:  Supreme Court ruling leaves wind-power line up in the air | By Steve Daniels | Crain's Chicago Business | September 21, 2017 | www.chicagobusiness.com ~~

The Illinois Supreme Court has dealt a punishing blow to the proposed clean-power “super highway” designed to transmit output from Iowa and Dakotas wind farms to the Chicago market.

The state’s high court today upheld an Illinois Appellate Court ruling​ that concluded state regulators improperly approved the Rock Island Clean Line project. (You can read the Supreme Court ruling at the end of this story.)

The $1.8 billion, 500-mile high-voltage line has been in the works for seven years. It appeared to clear a significant hurdle in late 2014 when the Illinois Commerce Commission ruled the developers had demonstrated there was a public need for their project—a necessary first step to potentially winning the right of eminent domain.

The ruling was challenged by landowners in the transmission line’s 120-mile path in Illinois, as well as Commonwealth Edison.

Opponents’ primary argument is that Clean Line Energy, the developer, isn’t a “public utility” in the legal sense of that term. Only public utilities can obtain the kind of certificate that the ICC granted the project.

In its unanimous opinion, the Supreme Court agreed with that argument, but made clear that Clean Line could reapply with the commission. A key aspect of the court’s objection was that Clean Line hadn’t yet acquired property near the proposed end of the transmission line to construct a facility that could convert the electricity for use in the power grid here. Instead, Clean Line has an option to buy the land.

Thus, the developers potentially could exercise that option and reapply with the commission. That would mean a minimum of 18 months’ delay.

“Talk about a legal hangnail,” said Hans Detweiler, Rock Island vice president of development.

They also could appeal to the U.S. Supreme Court.

Clean Line will decide on whether to continue to press ahead in the coming months, Detweiler said.

‘COMPETITION IMPACT’

In a statement, Clean Line said, “This (ruling) causes great delay for the project and will directly impact competition in electricity markets, resulting in fewer choices and higher prices for electricity. It is unfortunate that Illinois now has higher barriers for new market entrants.”

Unlike most high-voltage lines, Clean Line’s wouldn’t require ratepayers in Illinois to pay higher electricity rates to cover the project’s costs. It’s a so-called merchant line, whose costs would be covered in fees paid by wind-farm owners to use it to transport their output to end users in more populated areas.

ComEd parent Exelon has been vocal about the negative effect wind farms to the west of Illinois have had on wholesale power prices here. That keeps electric bills relatively low in Illinois, but hurts the profitability of Exelon’s fleet of Illinois nuclear plants. A law signed late last year by Gov. Bruce Rauner subsidizes two of those six nukes via a surcharge on electric bills throughout the state that will funnel $235 million of additional revenue to Exelon.

Even if Rock Island Clean Line ultimately can win approval in Illinois, it still must do the same in Iowa. The developers haven’t begun the process necessary to get land rights in Iowa because they were waiting to see what would happen in the Illinois courts.

Source:  Supreme Court ruling leaves wind-power line up in the air | By Steve Daniels | Crain's Chicago Business | September 21, 2017 | www.chicagobusiness.com

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI M TG TS G Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky