LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

Black Fork wind farm gets construction extension 

Credit:  Todd Hill, Reporter | Telegraph-Forum | March 28, 2016 | www.bucyrustelegraphforum.com ~~

BUCYRUS – Opponents of the planned Black Fork wind farm in northern Crawford and Richland counties have been fighting the project ever since the first of three developers began acquiring land rights back in 2007.

They have had some success at delaying it, although market forces in the energy sector have had a lot more to do with the fact that there are still no wind turbines sticking up out of the ground between Shelby and Tiro.

Last week, however, opponents of the project lost a battle in their years-long war against the wind turbines.

Black Fork Wind Energy, the legal name for the project now being shepherded by Capital Power, has been granted a two-year extension of its certificate of environmental compatibility and public need from Jan. 23, 2017, to the same date in 2019. The decision was handed down late last week by the Ohio Power Siting Board.

Black Fork had sought the extension for two reasons. It contended that the opponents’ legal actions had kept the project from moving forward. “And also … Black Fork’s ability to proceed with the project has been hampered by recent energy market changes in Ohio,” the OPSB’s decision read.

“Black Fork asserts that together these two factors have undercut Black Fork’s ability to enter into an economic power purchase agreement for the project’s energy and renewable energy credits at a price sufficient to support construction and financing of the project.”

Black Fork said a surge in the supply of natural gas from shale, particularly that originating from eastern Ohio and western Pennsylvania, as well as decreased demand for electricity, have made landing a power purchase agreement, or PPM, challenging.

The Black Fork wind farm, consisting of turbines about 500 feet tall, would be spread out across 14,800 acres of private land leased from 150 landowners west of Shelby, north of Crestline and almost surrounding the tiny village of Tiro. The project would be laid out like an X, with a substation in the middle.

Capital Power’s Bill Behling, during visits in recent weeks with Crawford and Richland county commissioners, said he’s optimistic that the first turbines will be in the ground later this year.

“We’ve moved forward with people wanting to buy power, which is a big aspect of this. We’ve had strong interest from both utilities and corporations,” Behling said.

Also, if Capital Power can begin construction before this year is over, it will receive a full allotment of federal tax credits. But even if that doesn’t happen, the project managers now have until 2019 to get started, courtesy of the OPSB’s decision.

Fighting the project almost from the beginning have been local residents Gary J. Biglin, Karel A. Davis, Brett A. Heffner, Margaret Rietschlin and John Warrington.

“The financial risk of Black Fork is disproportionately placed upon the lifelong residents of the project area. The greatest investment of the lives of 1,413 residents is subject to noise effects and 604 homes are subject to shadow-flicker effects,” Warrington, who lives on Ohio 96 near Tiro, wrote in one legal objection.

The OPSB’s initial certificate required project managers to commence construction by Jan. 23, 2017. Black Fork has argued that can’t occur until after market conditions improve, allowing project financing to then take place.

Biglin, in arguing against the certificate extension, said that waiting until wind-generated power becomes economically viable in Ohio “is not good cause to limit efficient land use of property for years to come.”

Project managers disagreed, pointing out “that no landowners who actually participate in its project have submitted public comments opposing the company’s request for certificate extension,” the OPSB said in its ruling.

Source:  Todd Hill, Reporter | Telegraph-Forum | March 28, 2016 | www.bucyrustelegraphforum.com

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI M TG TS G Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky