€200m wind farm decision will not be revealed today
Credit: €200m wind farm decision will NOT be revealed today | By Chris Ashmore | Friday 30th of October 2015 | Donegal Now | www.donegalnow.com ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
A ruling on whether to grant planning permission for a controversial €200m wind farm in east Donegal will not be given today, Donegal Now can reveal.
Cork-based company Planree Limited wants to erect 49 wind turbines over a 15 km area stretching from north of the Barnsemore Gap to near Killygordon.
Under the fast-tracking Strategic Infrastructure Development (SID) process, the planning application by-passed Donegal County Council and was lodged directly with An Bord Pleanala in January.
The Carrickaduff windfarm proposals promoted considerable local debate and over 200 objections were made.
Originally a decision was scheduled for today.
However, a spokesman for An Bord Pleanala confirmed to Donegal Now that there will be no decision today.
The applicant has provided further information in response to the third party submissions and this is now being examined.
A decision will now not be made for a number of weeks.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
(via Stripe) |
(via Paypal) |
Share: