LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Paypal

Donate via Stripe

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

Trouble in the wind 

Credit:  Ruling expected within weeks on Texas oil ­tycoon’s NAFTA challenge of wind farm deals | By John Miner, The London Free Press | Monday, October 26, 2015 | www.lfpress.com ~~

It’s a high-stakes legal battle over London-area wind farms that pits a self-proclaimed, Canada-loving, Texas oil tycoon against the federal government.

Mesa Power Group LLC vs. Government of Canada, a case that could leave taxpayers on the hook for hundreds of millions of dollars in damages, is expected to be ruled on within weeks, four years after the claim was launched by T. Boone Pickens under the North American Free Trade Agreement.

Though the federal government is the defendant, Pickens’ real quarrel is with Ontario.

In submissions and testimony before the NAFTA panel hearing the arbitration case, Pickens’ company claims it failed to win contracts for four massive wind farms in Huron and Bruce counties in Southwestern Ontario because of political interference at the highest level.

“This whole process was not carried out in good faith. This was not honesty. This was not fairness. This process was infused with raw politics, arbitrariness, and an egregious abuse of authority,” Mesa lawyer Barry Appleton said in his closing submission to the panel’s three arbitrators at a hearing in Toronto in October 2014.

The claim contains allegations that have not been proven.

In his own testimony before the NAFTA arbitrators, Pickens described how he was a big fan of Canada because of its rule of law.

“My experiences were so good that I enjoyed telling people about it,” he said, relating how he came to Canada with less than $100,000 in 1959 and sold out 20 years later for $610 million.

But his experience in Ontario left him disappointed, he said.

“You always feel bad when you lose, and then you look to see why you lost, and here we lost because we didn’t have a level playing field,” Pickens testified.

Home to Ontario’s largest wind farms with its largest number of the highrise-sized turbines, Southwestern Ontario is no stranger to the controversies generated by the power-producing windmills. Critics have decried them as a threat to human health, divisive to rural communities and a financial blow to a province that signed up producers with early sweetheart deals paying them far more to generate power than consumers pay.

Details of this latest dust-up are found on a federal government website containing submissions by Mesa, the governments of Canada, the U.S. and Mexico, and transcripts of the claim heard before a NAFTA tribunal last fall.

Mesa argued that other wind farm companies, Florida-based NextEra Energy and Korean-based Samsung – both, industry giants – were given illegal, preferential treatment and inside information that doomed Mesa’s projects.

“It was a cesspool. It was shameful. I feel very badly after seeing what went on here for my fellow Ontarians and the ratepayers of Ontario. They are having to bear the burden of the shameful behaviour,” Appleton said in a transcript from the hearing.

Responding to Mesa’s arguments, also at the hearing, Canada’s lawyers rejected Mesa’s assertions and said the company’s failures were self-inflicted.

“This is a case which is, as the expression goes, about sour grapes. It is a case about an investor who took a business risk and is unwilling to accept that that risk did not pay off,” government of Canada lawyer Shane Spelliscy said.

Spelliscy said Mesa’s applications for contracts with the Ontario Power Corp. were “sloppy” and “poorly done.”

When contracts were handed out, Mesa didn’t get one because its proposals weren’t highly ranked in a process monitored by an independent third party, Spelliscy said.

If they had put together better applications, they may have been successful, the federal lawyer said.

“There was no discrimination,” he said.

According to Mesa’s submissions, it decided to develop wind farms in Ontario – one, a 200-megawatt proposal in Bruce County would have been the largest in Ontario – after learning the province was offering 20-year contracts at a fixed price of 13.5 cents per kilowatt-hour.

“Make no doubt about this, this was a highly attractive rate,” said Appleton.

The rate meant there was no shortage of competing applications. A critical factor for companies became whether there would be enough transmission capacity for wind energy in the areas where they’d selected to build.

Appleton said Mesa had no idea that Ontario had cut a separate deal to allocate transmission capacity to Samsung, a Korean industrial giant, which promised to build manufacturing plants in Ontario.

And Mesa, unlike some of its competitors, was never informed about rule changes, a chance to switch its transmission points in order to increase its chances, he said.

Part of Mesa’s case was based on e-mails from Bob Lopinski, a registered lobbyist for NextEra, to Energy Ministry officials during the allocation process.

Lopinksi, a principal at Counsel Public Affairs, had previously served as director of issues management and legislative affairs to then-premier Dalton McGuinty and advised the Liberal leader on selecting cabinet ministers.

Appleton said though Lopinski and NextEra executives were communicating with Ontario government and Hydro One officials, Mesa understood no such communication was allowed.

Canada’s response filed with the NAFTA panel was there isn’t any evidence NextEra was ever provided with non-public information.

Mesa has asked for damages of $653 million plus interest.

READ THE DOCUMENTS

Legal documents from Mesa’s lawsuit against Canada under Chapter 11 of NAFTA can be found at: http://www.international.gc.ca/trade-agreements-accords-commerciaux/topics-domaines/disp-diff/mesa.aspx?lang=eng

MESA’S four PROPOSED WIND FARMS

The company claims it already invested $160 million on preliminary work for four proposed wind farms in western Ontario and would have spent $1.2 billion-plus on construction:

Twenty Two Degree: 150-megawatt project

Arran Wind Energy: 115-MW project

Summerhill: 100-MW project

North Bruce: 200-MW project

Source:  Ruling expected within weeks on Texas oil ­tycoon’s NAFTA challenge of wind farm deals | By John Miner, The London Free Press | Monday, October 26, 2015 | www.lfpress.com

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Paypal
(via Paypal)
Donate via Stripe
(via Stripe)

Share:

e-mail X FB LI TG TG Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook

Wind Watch on Linked In Wind Watch on Mastodon