NextEra says broken wind turbine blade removed
Credit: By Caitlin Mullen, Daily Chronicle, www.daily-chronicle.com 5 May 2011 ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
SHABBONA – Officials with NextEra Energy said a broken blade on a wind turbine has been removed and the cause of the shattered blade will be investigated. With weight limits on county and township roads this spring, NextEra spokesman Steve Stengel said Thursday that the company had to wait until those weight postings were removed before a large truck with a crane could drive on the roads to get to the blade, at Shabbona Road between Keslinger and Gurler roads.
The DeKalb County Highway Department removed its spring road posting signs for county roads April 8, which had restricted traffic weighing more than 33,000 pounds, County Engineer Bill Lorence said.
Stengel, who said broken blades occur occasionally, with one happening in May 2010, said the blade was removed in the last 1½ weeks. It shattered in mid-March. The company has operated 145 turbines in DeKalb and Lee counties since late 2009. A group of local residents called Citizens for Open Government is opposed to the wind farm and is suing to have it shut down.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
(via Stripe) |
(via Paypal) |
Share: