Officials uphold denial of turbine permit
Credit: By Sandi Hoover, Nevada Appeal, www.nevadaappeal.com 5 March 2011 ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
A planning commission denial of a permit to build a 160-foot wind turbine in southeast Carson City was upheld by the Carson City Board of Supervisors on Thursday.
Luke Busby, lawyer for Rainbow Conservation Corps, doing business as the Solar Store, told supervisors that the efficiency of a shorter model would “substantially compromised.”
The proposed turbine was for Joe Goni on property zoned single-family 6,000 at 7300 Schulz Drive.
He also told the board he believed the city’s height, setback and noise standards might not be enforceable under state statutes which say that local governments must not interfere with the efficiency of renewable energy efforts.
Supervisors, however, disagreed.
“We have OK’d other (wind turbines),” said Supervisor Shelly Aldean, in making the motion to uphold the planning commission’s ruling, “and I believe our code is enforceable.”
Supervisors were unanimous in their vote.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
(via Paypal) |
(via Stripe) |
Share: