Damages delay construction of first M’Chigeeng windmill
Credit: By Stacey Lavallie, The Manitoulin Expositor, www.manitoulin.ca 2 November 2011 ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
M’CHIGEENG—A faulty piece of equipment has delayed the attachment of the rotor and blades to the first turbine under construction in M’Chigeeng, according to Mother Earth Renewable Energy project supervisor Grant Taibossigai.
“It’s a safety concern,” he said about the delay. “A piece isn’t locking into position, so they (the construction company) have sent for a replacement part.”
He said the part should be in by the end of the week, but in the meantime, the crew is moving to the next turbine site to start erecting the second turbine.
According to Mr. Taibossigai, the project is still on schedule.
“It’s been a very safe work site,” he said, noting that no one has been injured on the job. He also praised his security staff, which is keeping the site secure.
Once the turbines are complete, the next step will be preparing them to be connected to the Ontario Hydro power grid.
The project is slated to be complete in early February 2012.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
(via Stripe) |
(via Paypal) |
Share: