LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Paypal

Donate via Stripe

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

Newing residents wary after Viking correspondence 

Credit:  Hans J Marter | Shetland News | 23 September 2021 | www.shetnews.co.uk ~~

Residents in the Newing area of South Nesting say they feel wind farm developer SSE Renewables might try to “fob us off” after receiving “no real answers to our queries, concerns and fears”.

The group of residents approached the owners of the Viking Energy wind farm earlier this summer after it emerged the developer was planning to create a large ‘borrow pit’ to extract stone for tracks and turbine bases less than 500 metres from their homes.

The homeowners have now received a written response from Viking Energy Wind Farm (VEWF) stakeholder manager Aaron Priest, but say they are less than reassured by the content of his letter.

Last months the residents went public with their concerns, saying they should have been directly consulted during the planning process.

In his letter Priest said the existence of a borrow pit near Skellister Loch had been part of the Viking Energy project since first consented by Scottish Ministers in 2012, as well as during a subsequent application seeking variations to the existing planning permission.

Priest went on saying that Nesting and Lunnasting Community Council had been “specifically consulted by Scottish Ministers for its opinion on the application to vary the consent (which included the borrow pit search area near Skellister Loch) and no representation was made”.

He said the presence of a borrow pit “has been consistent throughout and I am not aware of a commitment being made, at any point, to remove it.”

The resident group, however, claims the developer is at fault and in breach of its own code of practise for noise and vibration consultation, known within the industry as BS5228.

Resident group spokeswoman Suzanne Malcolmson said the “community relations” section of BS5228 emphasises that “good relations with people living and working in the vicinity of site operations are of paramount importance”.

“It is suggested that good relations can be developed by keeping people informed of progress and by treating complaints fairly and expeditiously,” the code of practice states.

Malcolmson said that rather than through the community council, householders affected by the five-acre quarry should have been consulted directly with.

She asked: “Is it appropriate for VEWF to pass the responsibility of community relations and the dissemination of information to the local community to a third party?

“And if that was their intention, have they provided sufficient guidance to community councils on how this should be done. It seems like they are ‘passing the buck’ and this is most definitely not in the spirit of community relation as outlined in BS5228.”

Priest said that the company and its main contractor RJ McLeod were currently undertaking an analysis to determine “whether or not there remains a need to access and utilise [borrow pit] NBP06”, adding there remained a strong possibility that the consented borrow pit would be developed.

He also confirmed that the company was willing to carry out and pay for “industry standard” dilapidation surveys of the houses in the vicinity of the borrow pit.

“The project would welcome the opportunity to meet the request for condition surveys, in advance of any requirement to develop NBP06, if the residents would wish this to go ahead,” he said.

Malcolmson said the group welcomed this concession but no details have been given as to “how and when” these surveys would be carried out and whether “they will be rectifying any damage”.

Priest added that the liaison process with the affected householders would now be formalised in that they will be kept updated and informed on a regular basis.

Malcolmson responded: “We welcome this but Aaron Priest does not say how they will do this, and we have had no proposals or suggestion to try and arrange a meeting with VE.

“We essentially think they are trying to fob us off, with no real answers to our queries concerns and fears.”

Source:  Hans J Marter | Shetland News | 23 September 2021 | www.shetnews.co.uk

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Paypal
(via Paypal)
Donate via Stripe
(via Stripe)

Share:

e-mail X FB LI TG TG Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook

Wind Watch on Linked In Wind Watch on Mastodon