[ exact phrase in "" ]

[ including uploaded files ]

ISSUES/LOCATIONS

List all documents, ordered…

By Title

By Author

View PDF, DOC, PPT, and XLS files on line
Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Paypal

Donate via Stripe

RSS

Add NWW documents to your site (click here)

Wind Watch is a registered educational charity, founded in 2005.

Wind Decommissioning Costs — Lessons Learned 

Author:  | Economics, West Virginia

Last month, EVA was hired by the Mountain Communities for Responsible Energy to evaluate a Decommissioning Cost Report prepared for the Beech Ridge Energy Project – a 124-turbine project proposed for Greenbrier County, West Virginia. The project wind developer (Invergy) had argued that the scrap value of the wind turbines would far exceed the cost to decommission the wind project and that therefore they should be responsible for bonding $2,500/turbine that would slowly escalate to $25,000/turbine by year 16.

EVA completed an independent estimate of the salvage value of the Beech Ridge Wind turbines. The applicant’s consultant estimated that its salvage value credit would reach $12.64 million ($101,900/turbine) in their decommissioning fund study based upon application of general scrap factors and prices. This scrap value credit would more than offset their estimated demo costs ($8.68 million: $70,000/turbine).

EVA contacted the major regional scrap yards directly and got current scrap prices for steel, copper and transport. From these data, EVA developed a Beech Ridge project–specific salvage credit estimate of only $2.63 million, i.e., $10.01 million less than the original applicant study. We uncovered several major flaws in the applicant study methodology and pricing. They not only used old scrap prices but failed to take into account that they would have to transport the scrap to a yard. In addition, to obtain the posted scrap price, they would need to break down the tower into 3-4 ft long pieces or else the quoted price would be significantly less. In addition, the copper materials must also have their insulation stripped and/or copper pieces separated to obtain their posted copper price. If not, their scrap value would be far less than the common posted price. Given the large drop in scrap prices this year (>40%), scrap value can no longer cover decommissioning costs.

EVA also compared the estimated demolition costs to another decommissioning report for another wind project developer that had contained detailed cost breakdowns. The other study estimated demo costs of $97K/turbine vs. $70K/turbine by Beech Ridge. The bottom line is that using the demolition costs from the other wind turbine project decommissioning study would translate to a Beech Ridge demo cost of $12.03 million, i.e., $3.35 million more the applicant’s $8.68 million estimate. (Note: In another very recent project I have just reviewed, the decommissioning costs were again severely underestimated by more than 50% by not taking into account recent crane rental rates, extremely low earth moving costs, and assuming high productivity rates (6 turbines/wk).)

The bottom line is that even if the permitting agency allows the salvage credit, the total net cost of decommissioning this project today would be $10.4 million ($83,900/turbine). Our analysis quantified the large scrap price and demo cost escalation risk being assumed by the local community. To protect the community, the permitting agency should require a bond of a minimum $100/K per turbine ($12.4 million) to capture demolition cost escalation risk. If the wind developer can convince the bonding company of the high salvage value, then they should be able to negotiate a lower rate for the bond. If they were right, there would be very little price difference for a larger $12+ million bond. Shift the risk to the bonding company. Let the developer and bonding company assume the price risk – not the community.

Tom Hewson
Principal
Energy Ventures Analysis
Arlington , VA
Hewson@evainc.com

See:  Decommissioning Estimate for the Green River Wind Farm Phase I

This material is the work of the author(s) indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this material resides with the author(s). As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Queries e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Paypal
(via Paypal)
Donate via Stripe
(via Stripe)

Share:

e-mail X FB LI TG TG Share

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook

Wind Watch on Linked In Wind Watch on Mastodon